Smith Mountain


AEP
Updated 8/07/08

On August 7, 2008, the FERC issued its Notice of Application Accepted for Filing, Intent to Prepare An Environmental Impact Statement, Soliciting Motions to Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions for the Smith Mountain Project. View notice

On July 14, 2008 Appalachian filed its Response to Request for Additional Information and revised Management Plans.

On May 16, 2008, the Federal Energy Regulatory Commission issued a letter requesting additional information in order for them to complete their environmental review of Appalachian's Application for New License.

Smith Mountain Project Relicensing Update
On April 9, 2008, the Federal Energy Regulatory Commission issued the Notice of Application Tendered for Filing with the Commission and Establishing Procedural Schedule for Licensing and Deadline For Submission of Final Amendments for the Smith Mountain Project No. 2210.

On March 26, 2008, Appalachian filed an application with the Federal Energy Regulatory Commission (FERC) for a new license to continue operation of the Smith Mountain Project (No. 2210) located on the Roanoke River in Bedford, Campbell, Franklin and Pittsylvania counties of Virginia

SMP Assignment Policy
Appalachian has clarified its Assignment Policy with regards to permits issued for docks. Applicable forms are available below.

Smith Mountain Shoreline Management Plan Update
On February 23, 2007, the Federal Energy Regulatory Commission issued an Order Amending Shoreline Management Plan allowing in-water construction to occur in areas other than those identified as Conservation/Environmental or Impact Minimization Zone from February 15 to June 15 each year for the remainder of the license (2010). Although shoreline stabilization may take place, dredging is prohibited. For additional information, please contact Appalachian Power Company at 540-489-2540..


Project Description
Project Re-Licensing
More Information
Smith Mountain Dam

Leesville Dam

FERC Project No. 2210

Shoreline Management Plan
Shoreline Management Plan Development
FERC Regulations & Guidelines